Step-by-Step Instructions

Set up an SOV for a subcontractor​

  1. Go to Accounting → Subcontracts SOV.
  2. Click Add new vendor and pick a vendor from the list. Only vendors already on the project are listed. The page switches to that vendor's SOV.
  3. Click the info icon next to the vendor name to check the contract, amount and retainage in Vendor overview.
  4. Continue with Add line items below.

Add line items​

  1. Click Unlock in the toolbar.
  2. In the group where the items belong, click Add New Row. A new empty row appears and the page scrolls to it.
  3. Fill in Pay item No., Owner pay item, Description, Unit, Units cost and the Contract estimated quantity. The amount is calculated for you.
  4. Click Save Changes. You see "Your changes have been saved".

Paste line items from a spreadsheet​

  1. In Excel or Google Sheets, arrange the columns in this order: Pay item No., Owner pay item, Description, Unit, Unit cost, Quantity. Extra columns to the right are ignored.
  2. Select the rows (without the header) and copy them.
  3. In the SOV, unlock the table and click Paste New Rows on the group where they belong. If your browser asks for permission to read the clipboard, allow it.
  4. Check the new rows. Units the system does not recognize are left at the default, so set them by hand.
  5. Click Save Changes.

Organize rows into groups​

  1. On the vendor row, click Create group.
  2. Enter a Group name and click Create. You see "Group created successfully".
  3. Hover over a row and click the Move row to group icon. Choose the group and click Move.
  4. To change the order of groups, click Reorder groups (or ⋮ → Reorder on a group), drag the groups into place and click Confirm.
  5. To rename or delete a group, open its ⋮ menu. Deleting a group keeps its rows and returns them to their original place in the table. You must save or discard other changes before you can create, reorder or move.

Bill work for the current period​

  1. Open the SOV. You do not need to unlock the table to bill.
  2. For each row, enter progress in Current pay estimate and, if needed, Materials currently stored. On lump-sum rows, enter a percent.
  3. Check JTD vs Contract and Remaining total on each row, and the totals at the bottom.
  4. Click Save Changes.

Generate a pay application​

  1. Make sure all changes are saved and no cell shows an error.
  2. Click Generate pay app. If any row is over 100% of its contract value, confirm with Generate anyway or click cancel to fix it.
  3. Summary: enter the Period to date and Signer, choose Draft or Certified, and review the totals.
  4. Project info: check contract number and addresses.
  5. Format: choose columns and sorting for the PDF.
  6. Voucher (subcontracts only, and only when the status is not Draft): attach a voucher if needed.
  7. Click Preview to check the PDF, then click Generate.
  8. You see "Pay application generated successfully." The new pay app appears under Pay Applications.

Change the billing rules​

  1. Save or discard any changes first.
  2. Click Contract settings.
  3. Choose the retainage type and value, contract date, stored materials rule, pay app starting number and supplier agreement limit.
  4. Click Save.

Remove a row​

  1. Save or discard other changes first (new, unsaved rows can be removed at any time).
  2. Hover over the row and click the red delete icon.
  3. Confirm in the Remove row dialog.